Considering dual rate method, if employees work for 8500 budgeted hours at $120 per hour, and work for 9500 actual hours at $110 per hour, then the total cost would be ____________? April 20, 2025 by admin A. $2,078,000 B. $3,078,000 C. $2,065,000 D. $3,065,000